Bridge Replacements

April 16, 2018 By jasonm

Replace 3 bridges on STH 80 North of Richland Center

B-52-269 over Fancy Creek

  • Just South of STH 56 intersection
  • Bridge is being constructed approximately 50′ west of existing structure
  • Work to begin 4/16/2018 and last until mid September
  • STH 80 and STH 56 to remain open except for a 10-day closure to move traffic over to the completed structure
  • A left turn lane will be added on STH 80 at the STH 56 intersection
  • New structure is a single span concrete girder bridge

B-52-270 over the Pine River

  • Just North of CTH D (East) intersection
  • Bridge is being constructed at same location
  • Work to begin April 30 and lasts until October (weather dependent)
  • Requires detour of STH 80 north of STH 80
  • New structure is a three- span concrete girder bridge

B-52-268 over the Pine River

  • Bridge in Rockbridge next to County Park
  • Bridge is being constructed in same location, new structure is one span longer
  • Work to begin in early May and last until October
  • New Structure is a six- span concrete slab structure

The Project Manager (contact person) is Dan Kleinertz, P.E. 608-789-5709

Filed Under: Projects

General Information

Josh Elder, Highway Commissioner

Office: 608-647-4707
Shop: 608-647-2208
Fax: 608-647-3231

Office Location

Richland County Highway Department
120 Bowen Circle
Richland Center, WI 53581

Important Links

National Weather Service
Wisconsin Travel Info
WRCO Radio

Copyright © 2025 Richland County Highway Department   All Rights Reserved.
Richland County, Wisconsin